A New Stage in the Construction Work on the EPR in China - Completion of the Installation of the Heavy Components At Taishan 1 - A successful partnership with the Chinese utility CGNPC - AREVA.com
A New Stage in the Construction Work on the EPR in China - Completion of the Installation of the Heavy Components At Taishan 1

 

NewswireToday - /newswire/ - Paris, France, 2013/01/22 - A successful partnership with the Chinese utility CGNPC - AREVA.com.

   
 
Your Banner Ad Here instead - Showing along with ALL Articles covering Energy Announcements

Replace these Affiliate Programs at ANYTIME! Your banner here within the next hour. Learn How!


 

During her visit today to the Taishan nuclear site (in Guangdong province), Mrs Nicole Bricq, the French Minister for Foreign Trade, accompanied by Luc Oursel, Chairman of AREVA’s Executive Board, and Henri Proglio, Chairman and CEO of EDF, was able to see for herself the progress made in the construction work on the two EPR reactors in China, carried out by the owner and future operator of the site, the Taishan Nuclear Power Joint Venture Company (TNPJVC), a 30% stake in which belongs to EDF, and the rest to CGNPC.

The building site for the 1st reactor has entered a significant new stage with the completion of the work installing the reactor vessel and the installation of four steam generators and the pressurizer inside the reactor building.

The two EPR reactors currently being built in Taishan are benefiting from the lessons learned at EPR reactor sites in Finland and France; the welding work on the primary circuit(1) was completed 30% quicker than at the Olkiluoto 3 site.

It is also thanks to the relationships forged since the start of the project with the Flamanville 3 site, and the way that French and Chinese skills have complemented each other, that the time between the first concrete being poured and the installation of the dome was cut to just 24 months.

Before the installation phase, the lessons learned from experience also helped to reduce the time taken to build the four steam generators, in France by 40% compared to those having been built for other EPR reactors, making the French nuclear industry more competitive.

At the end of the tour of the site, Luc Oursel announced: “The completion of the installation of the heavy components is a major step forward in the construction of the first EPR reactor in China. Completed in just 38 months from the time the first concrete was poured, this shows that the work is being done in excellent conditions, and that it is benefiting from the experience that we have gained at other EPR sites as well as the quality of the partnership with CGNPC. I am delighted that the Minister has been able to see the progress of the construction work.”

Henri Proglio announced: “The installation of the heavy components at Taishan reactor no. 1 demonstrates the extent to which 2012 was a year full of major progress for the EPR site in China. Of course we owe this to the balanced collaboration between the French and the Chinese”.

(1) The primary circuit of the EPR reactor is made up of 4 identical loops connected to the vessel, each one including a steam generator, a pump and the associated pipes.

Contacts

Press:
EDF - Carole Trivi & Aurélien Cassuto: + 33 1 40 42 46 37

Analysts and investors:
EDF - Carine de Boissezon: + 33 1 40 42 45 53 / David Newhouse: + 33 1 40 42 32 45

Investor relations:
AREVA - Marie de Scorbiac: +33 1 34 96 05 97

 
 
Your Banner Ad Here instead - Showing along with ALL Articles covering Energy Announcements

Replace these Affiliate Programs at ANYTIME! Your banner here within the next hour. Learn How!


 

Written by / Agency / Source: AREVA

 
 

Availability: All Regions (Including Int'l)

 

Traffic Booster: [/] Quick Newswire Today Visibility Checker

 

Distribution / Indexing: [+] / [Company listed above is a registered member of our network. Content made possible by PRZOOM / PRTODAY indexing services]

 
 
# # #
 
 
  Your Banner Ad showing on ALL
Energy articles,
CATCH Visitors via Your Competitors Announcements!


A New Stage in the Construction Work on the EPR in China - Completion of the Installation of the Heavy Components At Taishan 1

Company website links NOT available to basic submissions
It is OK to republish and/or LINK any newswire for any legitimate media purpose as long as you name Newswire Today and LINK as the source.
 
  Is this your article?
Activate ALL web links and social stream by Upgrading to Press Release PREMIUM Plan Now!

AREVA |
Publisher Contact: Patricia Marie / Vincent Kempkes - AREVA.com 
+33(0)1 34 96 12 93
 
Newswire Today - PRZOOM / PRTODAY disclaims any content contained in this article. If you need/wish to contact the company who published the current release, you will need to contact them - NOT us. Issuers of articles are solely responsible for the accuracy of their content. Our complete disclaimer appears here.
IMPORTANT INFORMATION: Issuance, publication or distribution of this press release in certain jurisdictions could be subject to restrictions. The recipient of this press release is responsible for using this press release and the information herein in accordance with the applicable rules and regulations in the particular jurisdiction. This press release does not constitute an offer or an offering to acquire or subscribe for any AREVA securities in any jurisdiction including any other companies listed or named in this release.

Energy via RSSAdd NewswireToday - PRZOOM Headline News to FeedBurner
Find who RetweetFollow @NewswireTODAY



Are you the owner of this article?, Turn it PREMIUM with your LOGO instead - and make it 3rd party Ads-Free! within the next hour!


Read Latest Articles From AREVA / Company Profile


Read Energy Most Recent Related Newswires:

PJB Spearheads Digital Energy for Indonesia with Deployment of GE Digital Power Plant Software
GE and Maersk Drilling Accelerate their Digital Partnership to Drive Industry Transformation
GE to Provide Digitally-enabled HA Power Plant and Services for Mexico's Tierra Mojada Project
Cisco and Enel Sign Agreement on Digitisation and Innovative Services
Enel and Seedstars Sign Cooperation Agreement to Identify Innovative Energy Access Startups in Africa
ENGIE Launches its First Ephemeral Campus
Enel Signs Agreement with US Company Amber Kinetics on Innovative Flywheel Storage System
Alternative Fuels, Carrefour and ENGIE are Joining Forces to Develop Biomethane in France
GE Renewable Energy and Fortum Sverige AB Sign Digital Hydro Pilot Agreement
GE Renewable Energy Announces Agreement to Provide Cube Hydro with Aerating Turbines
GE Oil & Gas and Eni East Africa Sign Long-term Partnership to Develop Gas Resources Offshore of Mozambique
RWE Turns to GE to Improve Flexibility and Performance
Liquefied Gas Pump Market to Record an Exponential CAGR by 2026 According to Persistence Market Research
GE and Solairedirect India Partner for the Next 25 Years
ENGIE Wins Major Contract with Transport for London

Boost Your Social Network
& Crowdfunding Campaigns


LIFETIME SOCIAL MEDIA WALL
NewswireToday Celebrates 10 Years in Business


PREMIUM Members


Visit  La Bella Bakery Artisan Bakery Arizona

Visit  MagLar, Inc.





 
  ©2017 Newswire Today — Limelon Advertising, Co.
Home | About | Advertise/Pricing | Contact | Investors | Privacy/TOS | Sitemap | FRANCAIS
newswire, PR press releases distribution service magazines engine news alert newsroom press room breaking news public relations articles company news alerts newswiredistribution ezine bizentrepreneur biznewstoday digital business report market search pr firms agencies reports distri-bution today investor relation successful internet entrepreneurs newswire distribution prtoday.com freenewswiredistribution asianewstoday bizwiretoday USA pr UK today - NOT affiliated with PRNewswire as we declined their partnership offer in 2013
 
PRTODAY & NewswireTODAY are NOT affiliated with USA TODAY (usatoday.com)