Flamanville 3 - EDF Update on Cost Forecast and Schedule Compliance - Following EDF’s announcement of the cost increase at completion of the Flamanville 3 EPR™ reactor (FA3), AREVA wishes to point out that this cost is not representative of the price of an EPR™ reactor in the series offered in the market today - AREVA.com
Flamanville 3 - EDF Update on Cost Forecast and Schedule Compliance

 

NewswireToday - /newswire/ - Paris, France, 2012/12/04 - Following EDF’s announcement of the cost increase at completion of the Flamanville 3 EPR™ reactor (FA3), AREVA wishes to point out that this cost is not representative of the price of an EPR™ reactor in the series offered in the market today - AREVA.com.

   
 
Your Banner Ad Here instead - Showing along with ALL Articles covering Energy Announcements

Replace these Affiliate Programs at ANYTIME! Your banner here within the next hour. Learn How!


 

As for the construction of Olkiluoto 3 in Finland, FA3 is faced with the difficulties inherent in a first-of-a-kind reactor, since the French reactor has not benefitted from experience gained on the Finnish construction project for reasons of industrial organization and schedule. The cost put forward by EDF is therefore that of a next-generation, first-of-a-kind reactor in France.

The Taishan 1 and 2 reactors under construction in China – respectively the third and fourth of this reactor system – are taking full advantage of the construction experience from the two first-of-a-kind EPR™ reactors in France and Finland.

By way of example, the number of engineering hours was reduced by more than half between the OL3 and Taishan projects, and the schedule from the first concrete pour to placement of the dome was reduced by 23 months, while steam generator manufacturing and delivery took two years less. The total construction schedule for the EPR™ reactors in China should thus be 40% shorter than that for OL3. Taishan 1 construction is currently the fastest of any reactor in the world, regardless of generation.

This experience factor is bolstered by AREVA’s continuous optimization of the EPR™ system through its “Competitive EPR™” program. The objective is to optimize the cost and the construction schedule of the EPR™ reactor by pooling certain engineering work, among other things.

The EPR™ reactor is currently the only reactor technology to have received construction permits in three countries (France, Finland and China), and its design will soon be certified in the United Kingdom and the United States.The findings of the supplementary safety assessments (SSA) recently conducted in France and elsewhere in Europe confirmed the EPR™ reactor’s major advances in safety, with key safety principles emerging from the Fukushima accident incorporated into its design.

 
 
Your Banner Ad Here instead - Showing along with ALL Articles covering Energy Announcements

Replace these Affiliate Programs at ANYTIME! Your banner here within the next hour. Learn How!


 

Written by / Agency / Source: AREVA

 
 

Availability: All Regions (Including Int'l)

 

Traffic Booster: [/] Quick Newswire Today Visibility Checker

 

Distribution / Indexing: [+] / [Company listed above is a registered member of our network. Content made possible by PRZOOM / PRTODAY indexing services]

 
 
# # #
 
 
  Your Banner Ad showing on ALL
Energy articles,
CATCH Visitors via Your Competitors Announcements!


Flamanville 3 - EDF Update on Cost Forecast and Schedule Compliance

Company website links NOT available to basic submissions
It is OK to republish and/or LINK any newswire for any legitimate media purpose as long as you name Newswire Today and LINK as the source.
 
  Is this your article?
Activate ALL web links and social stream by Upgrading to Press Release PREMIUM Plan Now!

AREVA |
Publisher Contact: Press Office - AREVA.com 
+33(0)1 34 96 12 15 press[.]areva.com
 
Newswire Today - PRZOOM / PRTODAY disclaims any content contained in this article. If you need/wish to contact the company who published the current release, you will need to contact them - NOT us. Issuers of articles are solely responsible for the accuracy of their content. Our complete disclaimer appears here.
IMPORTANT INFORMATION: Issuance, publication or distribution of this press release in certain jurisdictions could be subject to restrictions. The recipient of this press release is responsible for using this press release and the information herein in accordance with the applicable rules and regulations in the particular jurisdiction. This press release does not constitute an offer or an offering to acquire or subscribe for any AREVA securities in any jurisdiction including any other companies listed or named in this release.

Energy via RSSAdd NewswireToday - PRZOOM Headline News to FeedBurner
Find who RetweetFollow @NewswireTODAY



Are you the owner of this article?, Turn it PREMIUM with your LOGO instead - and make it 3rd party Ads-Free! within the next hour!


Read Latest Articles From AREVA / Company Profile


Read Energy Most Recent Related Newswires:

Enel and Luxottica Group Inaugurate Innovative Mini-biomass Plant in Northern Italian Town of Agordo
The Abraaj Group and ENGIE to Develop a Wind Power Platform in India
Enel Starts Operation of South America's Two Largest Solar Parks in Brazil
Anheuser-Busch and Enel Green Power Announce Renewable Energy Partnership
EDP Renováveis and ENGIE Consortium Awarded Long-term CfD for 950 MW Offshore Wind Project in UK
E-Distribuzione Installs over A Million Electronic 2.0 Open Meters
ENGIE, through its Subsidiary ENGIE Axima, has Opened Exclusive Negotiations to Buy MCI, French Specialist in Industrial and Commercial Refrigeration
Enel Starts Construction of Peru’s Largest Wind Farm
GE Hits 5GW Milestone of Wind Energy in Brazil
Enel Starts Operations of Delfina Wind Farm in Brazil
GE to Install Advanced Wind Turbines for 150 MW Clean Power Project in Pakistan’s Jhimpir Corridor
ENGIE to Develop its First Renewable Project in Mongolia
Enel Starts Construction of Ayanunga Hydro Plant in Peru
Sundance Square and Green Mountain Energy Announce Extended Clean Energy Partnership
Enel Signs Tax Equity Agreement for 300 MW Red Dirt Wind Project in the USA

Boost Your Social Network
& Crowdfunding Campaigns


LIFETIME SOCIAL MEDIA WALL
NewswireToday Celebrates 10 Years in Business


PREMIUM Members


Visit  BizJobs.com

Visit  SKS Media | SKS Associates Ltd





 
  ©2017 Newswire Today — Limelon Advertising, Co.
Home | About | Advertise/Pricing | Contact | Investors | Privacy/TOS | Sitemap | FRANCAIS
newswire, PR press releases distribution service magazines engine news alert newsroom press room breaking news public relations articles company news alerts newswiredistribution ezine bizentrepreneur biznewstoday digital business report market search pr firms agencies reports distri-bution today investor relation successful internet entrepreneurs newswire distribution prtoday.com freenewswiredistribution asianewstoday bizwiretoday USA pr UK today - NOT affiliated with PRNewswire as we declined their partnership offer in 2013
 
PRTODAY & NewswireTODAY are NOT affiliated with USA TODAY (usatoday.com)