Flamanville 3 - EDF Update on Cost Forecast and Schedule Compliance - Following EDF’s announcement of the cost increase at completion of the Flamanville 3 EPR™ reactor (FA3), AREVA wishes to point out that this cost is not representative of the price of an EPR™ reactor in the series offered in the market today - AREVA.com
Flamanville 3 - EDF Update on Cost Forecast and Schedule Compliance

 

NewswireToday - /newswire/ - Paris, France, 2012/12/04 - Following EDF’s announcement of the cost increase at completion of the Flamanville 3 EPR™ reactor (FA3), AREVA wishes to point out that this cost is not representative of the price of an EPR™ reactor in the series offered in the market today - AREVA.com.

   
 
Your Banner Ad Here instead - Showing along with ALL Articles covering Energy Announcements

Replace these Affiliate Programs at ANYTIME! Your banner here within the next hour. Learn How!


 

As for the construction of Olkiluoto 3 in Finland, FA3 is faced with the difficulties inherent in a first-of-a-kind reactor, since the French reactor has not benefitted from experience gained on the Finnish construction project for reasons of industrial organization and schedule. The cost put forward by EDF is therefore that of a next-generation, first-of-a-kind reactor in France.

The Taishan 1 and 2 reactors under construction in China – respectively the third and fourth of this reactor system – are taking full advantage of the construction experience from the two first-of-a-kind EPR™ reactors in France and Finland.

By way of example, the number of engineering hours was reduced by more than half between the OL3 and Taishan projects, and the schedule from the first concrete pour to placement of the dome was reduced by 23 months, while steam generator manufacturing and delivery took two years less. The total construction schedule for the EPR™ reactors in China should thus be 40% shorter than that for OL3. Taishan 1 construction is currently the fastest of any reactor in the world, regardless of generation.

This experience factor is bolstered by AREVA’s continuous optimization of the EPR™ system through its “Competitive EPR™” program. The objective is to optimize the cost and the construction schedule of the EPR™ reactor by pooling certain engineering work, among other things.

The EPR™ reactor is currently the only reactor technology to have received construction permits in three countries (France, Finland and China), and its design will soon be certified in the United Kingdom and the United States.The findings of the supplementary safety assessments (SSA) recently conducted in France and elsewhere in Europe confirmed the EPR™ reactor’s major advances in safety, with key safety principles emerging from the Fukushima accident incorporated into its design.

 
 
Your Banner Ad Here instead - Showing along with ALL Articles covering Energy Announcements

Replace these Affiliate Programs at ANYTIME! Your banner here within the next hour. Learn How!


 

Written by / Agency / Source: AREVA

 
 

Availability: All Regions (Including Int'l)

 

Traffic Booster: [/] Quick Newswire Today Visibility Checker

 

Distribution / Indexing: [+] / [Company listed above is a registered member of our network. Content made possible by PRZOOM / PRTODAY indexing services]

 
 
# # #
 
 
  Your Banner Ad showing on ALL
Energy articles,
CATCH Visitors via Your Competitors Announcements!


Flamanville 3 - EDF Update on Cost Forecast and Schedule Compliance

Company website links NOT available to basic submissions
It is OK to republish and/or LINK any newswire for any legitimate media purpose as long as you name Newswire Today and LINK as the source.
 
  Is this your article?
Activate ALL web links and social stream by Upgrading to Press Release PREMIUM Plan Now!

AREVA |
Publisher Contact: Press Office - AREVA.com 
+33(0)1 34 96 12 15 press[.]areva.com
 
Newswire Today - PRZOOM / PRTODAY disclaims any content contained in this article. If you need/wish to contact the company who published the current release, you will need to contact them - NOT us. Issuers of articles are solely responsible for the accuracy of their content. Our complete disclaimer appears here.
IMPORTANT INFORMATION: Issuance, publication or distribution of this press release in certain jurisdictions could be subject to restrictions. The recipient of this press release is responsible for using this press release and the information herein in accordance with the applicable rules and regulations in the particular jurisdiction. This press release does not constitute an offer or an offering to acquire or subscribe for any AREVA securities in any jurisdiction including any other companies listed or named in this release.

Energy via RSSAdd NewswireToday - PRZOOM Headline News to FeedBurner
Find who RetweetFollow @NewswireTODAY



Are you the owner of this article?, Turn it PREMIUM with your LOGO instead - and make it 3rd party Ads-Free! within the next hour!


Read Latest Articles From AREVA / Company Profile


Read Energy Most Recent Related Newswires:

Mexican Ministry of Energy Awards Three Geothermal Exploration Permits - A Key Step Forward for ENGIE and Reykjavik Geothermal
GNF3 Fuel Product Completes U.S. NRC Approved Process for New Fuel Product Introductions
Surging Demand from Data Centres Energises European Diesel Genset Market Finds Frost & Sullivan
Forestalia Selects GE Renewable Energy to Provide 1,200 MW of Wind Power in the Largest European Auction to Date
Enel Launches E-Solutions - A New Global Business Line
Enel Buys A Stand-alone Battery Energy Storage Project in UK
GE Supports Power Grids of the Future with Europe’s First MVDC Link
ENGIE Launches Home Energy Business in the UK
Akenerji Selects GE’s Predix-based Operations Optimization Software to Improve Gas Thermal Plant Efficiencies and Performance
Enel Starts Construction of New 298 MW Wind Project in The United States
OPEC and Non-OPEC Nations Will Reduce Oil & Gas Production to Restore Supply-Demand Parity Finds Frost & Sullivan
ENGIE and AES Agree to Expand their LNG Marketing Partnership to Central America
GE to Supply Power Generation Technology for Ghana’s 400 MW Bridge Power Project
Enel Starts Operating New South African Wind Farm
GE Announces Order with AE Energia to Bring Fast, Digital Power to Angola

Boost Your Social Network
& Crowdfunding Campaigns


LIFETIME SOCIAL MEDIA WALL
NewswireToday Celebrates 10 Years in Business


PREMIUM Members


Visit  Intrinsic Executive Search Ltd

Visit  NAKIVO, Inc.





 
  ©2017 Newswire Today — Limelon Advertising, Co.
Home | About | Advertise/Pricing | Contact | Investors | Privacy/TOS | Sitemap | FRANCAIS
newswire, PR free press releases distribution service magazines engine news alert newsroom press room breaking news public relations articles company news alerts newswiredistribution ezine bizentrepreneur biznewstoday digital business report market search pr firms agencies reports distri-bution today investor relation successful internet entrepreneurs newswire distribution prtoday.com freenewswiredistribution asianewstoday bizwiretoday USA pr UK today - NOT affiliated with PRNewswire as we declined their partnership offer in 2013
 
PRTODAY & NewswireTODAY are NOT affiliated with USA TODAY (usatoday.com)